Three hydel power projects to be completed next year

Published
0

PESHAWAR: Work on three hydel power projects with a total power generation capacity of 62.8 megawatts in Khyber Pakhtunkhwa will be completed by June next year.

The projects include 10.2 megawatts Jabori, 11.2 megawatts Karora and 40.8 megawatts Koto hydropower projects. On completion, these projects are expected to generate annual revenue of Rs2.73 billion, according to an official statement issued here on Tuesday.

Pakhtunkhwa Energy Development Organisation (Pedo) is the executing body of these projects. Progress on these projects was discussed in a meeting held here with Chief Minister Mahmood Khan in the chair.

The meeting was informed that work on other four important projects was also in progress. These include 84 megawatts Mataltan, 69 megawatts Lavi, 10 megawatts Chapri Charkhel and 6.5 megawatts Barando hydropower projects.

The meeting was also apprised of hydropower projects being executed through foreign aid in the province. It was told that progress was under way on 300 megawatts Balakot, 88 megawatts Gabral Kalam and 157 megawatts Madain hydropower projects.

The meeting was informed that under the first phase of the project, a total of 328 feasible schemes were identified out of which 281 mini-micro hydropower projects were completed so far.

Under the second phase, progress on a number of new micro hydropower projects is under way. Consultants have been hired for 317 micro hydropower projects on streams in Malakand and Hazara divisions and for 43 schemes on canals in other parts of the province.

Under the solarisation projects, seven schemes are in progress. Under the project, 2,956 mosques have been solarised in the province. Work on 13 solar mini grid stations in tribal districts is also in progress.

The meeting was informed that solarisation of 6,983 schools and 134 basic health units was also completed in the province.

Speaking on the occasion, the chief minister directed the commissioners and deputy commissioners concerned to clear all the matters related to acquisition of land for Balakot and Kalam hydropower projects within a month.

He said that the land after clearance should be handed over to the relevant department without any delay.

Published in Dawn, November 24th, 2021

Opinion

Editorial

Fixing bond markets
Updated 01 Oct, 2026

Fixing bond markets

Pension funds, insurance companies, mutual funds, retail investors, and eventually, foreign investors must become bigger participants in the market.
Call centre rackets
01 Oct, 2026

Call centre rackets

A NUMBER of recent raids conducted by the authorities in different cities point to the growing threat fraudulent ...
Homeward bound
01 Oct, 2026

Homeward bound

FIVE months after Somali pirates captured an oil tanker carrying a 19-member multinational crew, Somali maritime...
Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...