PESHAWAR: Auditors have detected a long delay in the revamping of district headquarters hospitals in Khyber Pakhtunkhwa despite the payment of Rs1.08 billion to the Infrastructure Development Authority of Punjab (IDAP) around three and a half years ago.

They recommended an investigation to determine responsibility and hold officials accountable.

In a report, the Auditor-General Khyber Pakhtunkhwa said a contract was signed between the KP health department and IDAP on June 30, 2021, under which the latter was required to execute “infrastructure improvement work” in 13 DHQ hospitals of the province under Phases I and II of the Revamping of the Non-Teaching District Headquarters Hospitals (DHQs) project.

The IDAP was bound by the agreement to start work on the revamping programme after receiving payment of 25pc “mobilisation advance” as per requirement of the agreement.

The annual audit of the records of the Directorate General Health Services Khyber Pakhtunkhwa for the financial year 2023-24 revealed that Rs1.08 billion was paid to IDAP on account of mobilisation advance for infrastructure improvement in 13 hospitals under the project.

Auditors recommend probe, accountability of culpable officials

Under the agreement, the health department was required to pay 25pc of the infrastructure improvement cost amounting to Rs2.8 billion and Rs4.37 billion for Phase I and Rs6.272 billion and Rs11.19 billion for Phase II.

However, the project management paid just Rs1.08 billion and IDAP refused to initiate infrastructure improvement work in the designated hospitals despite a lapse of three and half years. The project’s steering committee, in its meeting on May 2, 2024, requested the termination of the agreement with IDAP and retrieval of the paid amount along with interest, according to the report.

It added that as a result of a lack of government interest coupled with financial constraints and ill-planning, work on infrastructure improvement wasn’t initiated by the contractor, leaving Rs1.08 billion cash “idle” with IDAP.

The auditors said the lapse occurred due to poor planning and lack of government interest, which led to the blocking of funds in light of the non-initiation of infrastructure improvement work.

According to General Financial Rule 12, a controlling officer must see not only that the total expenditure is kept within the limits of the authorised appropriation but also that the funds allotted to spending units are spent in the public interest and on work for which the money was provided.

In order to maintain proper control, the officer should arrange to be kept informed, not only of what has actually been spent from an appropriation but also what commitments and liabilities have been and will be incurred against it. The officer must be in a position to assume before the government and the Public Accounts Committee, if necessary, complete responsibility for departmental expenditure and to explain or justify any instance of excess or financial irregularity that may be brought to notice as a result of audit scrutiny or otherwise.

The report said the auditors pointed out the matter in Nov 2024 but there was no reply from relevant quarters, so they recommended proper investigation to fix responsibility for “ill-planning and lack of financial oversight” so that the officials involved should be held accountable.

Published in Dawn, March 12th, 2025

Opinion

Editorial

Fixing bond markets
Updated 01 Oct, 2026

Fixing bond markets

Pension funds, insurance companies, mutual funds, retail investors, and eventually, foreign investors must become bigger participants in the market.
Call centre rackets
01 Oct, 2026

Call centre rackets

A NUMBER of recent raids conducted by the authorities in different cities point to the growing threat fraudulent ...
Homeward bound
01 Oct, 2026

Homeward bound

FIVE months after Somali pirates captured an oil tanker carrying a 19-member multinational crew, Somali maritime...
Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...