78pc work on Neelum-Jhelum project complete

Published
0

LAHORE: The progress on Neelum-Jhelum Hydro Project stands at 78.5 per cent, and the tunnel boring machines (TBM), which suffered rock burst on May 31 last year, were restored in the second week of January.

Chief Executive Officer Engineer Muhammad Zubair told the Wapda chairman during a visit to the site on Friday. Chairman Zafar Mahmood asked the project authorities to further expedite their efforts to meet the revised schedule.

As per revised schedule, first generating unit of the project is expected to be completed in July 2017, whereas the remaining three units will come on line by the end of 2017 in different phases.

Speaking on the occasion, the chairman appreciated the commitment and devotion of the project authorities in implementing this extremely precarious project. He said that most of the critical targets relating to construction of the project had been successfully achieved, therefore, Wapda was confident to complete it as per the timelines.

During the visit, the chairman also witnessed excavation of tunnel through the TBM at rock burst site. The chief executive officer apprised the chairman that both TBMs deployed at the project had been functioning satisfactorily. He further informed the chairman that installation of three hydraulic gates at the dam site (Nauseri, Neelum Valley) shall be completed by 15 March 2016..

The Neelum Jhelum Hydropower Company is constructing a world class underground power generation facility. The project envisages 90 per cent construction work under high mountainous overburden and only 10 per cent above the surface.

The project, on its completion, will contribute 5.15 billion units of low-cost and environment friendly electricity to the national grid.

Published in Dawn, March 12th, 2016

Opinion

Editorial

Fixing bond markets
Updated 01 Oct, 2026

Fixing bond markets

Pension funds, insurance companies, mutual funds, retail investors, and eventually, foreign investors must become bigger participants in the market.
Call centre rackets
01 Oct, 2026

Call centre rackets

A NUMBER of recent raids conducted by the authorities in different cities point to the growing threat fraudulent ...
Homeward bound
01 Oct, 2026

Homeward bound

FIVE months after Somali pirates captured an oil tanker carrying a 19-member multinational crew, Somali maritime...
Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...