Govt seeks fresh financing plan for ML-1 section

Published
0
Planning Minister Ahsan Iqbal chairs a meeting of a committee on ML-1 financing on August 28, 2026. — PID
Planning Minister Ahsan Iqbal chairs a meeting of a committee on ML-1 financing on August 28, 2026. — PID

ISLAMABAD: The proposed construction of the 460km Rohri-Multan section of the long-delayed Karachi-Peshawar Main Line-1 railway project, estimated to cost more than Rs450 billion, came under review on Friday as the government explored financing options other than the long-awaited Chinese funding.

A high-level committee led by Planning and Development Minister Ahsan Iqbal did not clear the proposal prepared by the Frontier Works Organisation (FWO) after noting that the cost of locomotives, coaches and their operation would be over and above the Rs450bn estimate for the railway section.

The minister also ordered an independent third-party review of the cost estimates.

“The meeting was also briefed on the proposal of the Frontier Works Organisation (FWO) to develop the Rohri-Multan section of ML-1 through private investment. The meeting was informed that the estimated cost of the Rohri-Multan section is over Rs450 billion,” an official statement said.

“The meeting reviewed various financing options for the completion of the ML-1 project, including the Public Sector Development Programme (PSDP), foreign financing, public-private partnership (PPP), financing through local commercial banks and the domestic capital markets,” it added.

The committee also deliberated on the formulation of a comprehensive financing plan for the project.

The meeting was held by a committee constituted on the prime minister’s directions to explore financing options for the Rohri-Multan section.

Mr Iqbal said the upgradation and modernisation of ML-1 remained a key government priority and called for a viable financing strategy.

Sources said the minister expressed displeasure over participation by some ministries at the additional secretary level and directed that federal secretaries attend the committee’s next meeting.

The railways secretary was asked to come up with a proper estimate for locomotives, coaches and other rolling stock, along with financing options and an assessment of how much funding Pakistan Railways could generate through its own marketing plan.

Mr Iqbal also directed that a comprehensive feasibility study be conducted by a credible independent third party to assess the project’s technical, financial and economic viability and help develop a sustainable financing model. According to the statement, the Ministry of Railways was also asked to assess future requirements for locomotives, freight rolling stock and passenger coaches, including the financing required, and incorporate them into an integrated plan.

The minister observed that continued reductions in the development budget were affecting projects of national importance, underscoring the need to make better use of available resources and explore alternative financing mechanisms.

The meeting was also briefed on the condition of the railway track and accidents attributed to deteriorating infrastructure.

Published in Dawn, August 29th, 2026

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Fixing bond markets
Updated 01 Oct, 2026

Fixing bond markets

Pension funds, insurance companies, mutual funds, retail investors, and eventually, foreign investors must become bigger participants in the market.
Call centre rackets
01 Oct, 2026

Call centre rackets

A NUMBER of recent raids conducted by the authorities in different cities point to the growing threat fraudulent ...
Homeward bound
01 Oct, 2026

Homeward bound

FIVE months after Somali pirates captured an oil tanker carrying a 19-member multinational crew, Somali maritime...
Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...