K-IV to miss another deadline if Sindh doesn’t get Rs25bn

Published
0

KARACHI: The Sindh caretaker government on Friday decided to approach the federal government for release of Rs25 billion to meet the ongoing expenditures on the much-awaited Greater Karachi Water Supply Scheme, commonly known as K-IV, fearing that shortage of funds was bound to delay the project.

Sources told Dawn the Rs23.1bn funds released earlier had already been spent on the overall 10 per cent work of the project, which was earlier scheduled to be completed by March 2024.

They said the released funds had been utilised and now Rs25bn more was required to meet the ongoing expenditures.

The work being carried out by the Water and Power Development Authority (Wapda) includes the construction of an intake structure for 650 million gallons per day (MGD) at Keenjhar Lake, establishment of Keenjhar Pumping Complex with the installation of two pumping stations, each one of 130 MGD, and a gravity channel of 650 MGD to it, development of pressurised pipeline conveyance with all appurtenant structures (260 MGD), and three reservoirs and filtration plants.

Caretaker finance minister Dagha says he will ask federal govt for funds’ release to meet project timeline

The decision to approach the federal government for funds was taken by Provincial Caretaker Finance Minister Muhammad Younus Dagha at a meeting on Friday.

Talking to Dawn, the minister said that the funds were required to be released so that the pace of the project could be continued. “If the funds are not released, the project is bound to be delayed,” he added.

The finance minister said he would request the federal government to release the funds so that the timeline of the project could be met.

He said that due to the delay in the implementation of the K-IV project, the citizens were facing a severe shortage of water.

Mr Dagha said that it was regrettable that the first phase of the K-IV project had not been completed so far.

He said that the project had been delayed due to cuts in the funds in the Public Sector Development Programme (PSDP).

The previous provincial government had set a timeline for starting the project in October and its completion and commissioning by November 2023.

Earlier in June, the Wapda had awarded three contracts of Rs98.5bn for construction of the Phase-I of K-IV.

Meanwhile, the finance minister chaired a review meeting on the clean drinking water, sewage and waste treatment systems of the city.

The minister, who also holds the portfolios of revenue, planning, and development, expressed dissatisfaction with the performance of water supply and sewage treatment schemes for the city.

He also directed the Karachi Water and Sewerage Corporation (KWSC) chief executive officer to promptly submit the scheme to the planning and development department in order to commence and complete the treatment plant in the shortest period.

The minister also reviewed the performance of the Sindh Solid Waste Management Board (SSWMB).

He directed that a third-party monitoring system should be implemented as soon as possible as per the rules to assess the performance of the contractor involved in the solid waste project.

Mr Dagha directed that payment be made to the contractor based on the report of the third-party monitoring system. Moreover, action should be taken against contractors performing poor, as per the rules.

He also directed that work on waste-to-electricity and waste recycling projects should also be expedited to improve the city’s environment.

Published in Dawn, August 26th, 2023

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...