Qesco completes first phase of tube well solarisation

Published
0

QUETTA: The Quetta Electric Supply Company (Qesco) has completed the first phase of its project to convert agricultural tube well connections to solar energy in the Quetta and Pishin districts.

As part of the initiative, Qesco disconnected the electrical connections of agricultural users who had received government funding for the solarisation programme.

By Jan 17, the company removed 494 transformers, 884 high-tension (HT) poles and other electrical equipment in Quetta and Pishin, effectively cutting these agricultural connections from its network.

However, Qesco faced resistance from some land owners, who failed to cooperate with the programme.

Instead of handing over their electrical equipment, certain landowners disconnected their tube well connections themselves and removed the transformers, poles and other equipment.

In some cases, landowners reportedly tampered with the equipment by removing components such as coils and oil and replacing them with stones, bricks and gravel to match the weight before returning the items to Qesco.

The company has urged provincial and district auth­orities to address the issue, as several landowners have yet to return the transformers and other equipment.

The first phase of the solarisation programme, which began on Dec 20, 2024, was funded with an allocation of Rs5.398 billion to facilitate the transition of 2,699 agricultural users to solar energy.

The initiative also uncovered 513 illegal agricultural connections, bringing the total disconnections to 3,212 in Quetta and Pishin.

A Qesco spokesperson said that out of the 2,699 connections, only 494 transformers, 884 HT poles and other equipment have been secured by the company, while a significant portion of the equipment was not unreturned by landowners.

The project aims to ensure that agricultural users transitioning to solar energy are fully disconnected from Qesco’s network. As part of this effort, the company removed transformers, HT poles and other electrical infrastructure to prevent unauthorised reconnection after the solarisation process.

Published in Dawn, January 22th, 2025

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...