Pehur canal project faces further delay

Published
0

SWABI: The Pehur High Level Canal Extension Project (PHLCEP) which was expected to bring “green revolution” in the district has been delayed for one and a half years due to various reasons including the paucity of funds, sources in the irrigation department told Dawn here on Sunday.

The project is financed by Asian Development Bank (ADB) with the contribution of Khyber Pakhtunkhwa’s government and its revised estimated cost in the current year has reached to Rs15.65 billion, the earlier estimated being Rs13.951 billion, but officials said that more prolong delay can increase its cost further, said the sources.

The construction activities on this project commenced in July 2017 and its completion was due in June 2024 but it has delayed while further delay could not be ruled out because the construction activities were not in a full swing. A visit to the project revealed that huge remaining work needed more time for completion, as still, regulators, siphons, drainage culverts, road bridges, supper passage, etc are to be built.

The project passes through lush green belts and at the time of land acquisition payment to the land owners was also one of the fundamental problems, said the sources, adding that the farmers accused the irrigation department officials that despite purchasing the land at throw away price the payment was delayed for long.

Sources said that the project is envisaged to irrigate through two main pressure pipes off taking from the Gandaf Tunnel of Tarbela Dam lake, about 8,727 hectare land situated at upper level which could not be irrigated from existing Pehur High Level Canal (PHLC).

The project covers two main areas:Janda Boka area about 1316 hectare and Ambar area comprises about 7411 hectare.

When contacted officials in district Irrigation department told Dawn that with the completion of PHLEP is expected to bring green revolution in the district, making KP self-sufficient in the wheat production.

Published in Dawn, December 22nd, 2025

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...