Concern voiced over slow work on Swabi medical college project

Published
0

SWABI: Representatives of the Gajju Khan Medical College Swabi have voiced concern over slow construction activities on the premises and demanded speedy work on the building.

The demand came as Dean Prof Shamsur Rehman chaired a meeting in his office regarding the GKMC building and the establishment of Gajju Khan Dental College.

The participants, including representatives of GKMC, communication and works department, consultants and contractors, discussed the delayed project and possible steps for its early completion.

They said the initial cost of the project was Rs2.6 billion but it increased as the project faced prolonged delay due to the government’s failure to release funds.

Officials of the communication and works department officials said the revised estimated expenditures were expected to be released soon.

Dean says contractor’s ‘delaying tactics’ no more acceptable

The participants decided that priority would be given to the academic block’s construction.

They said the Bacha Khan Hospital, too, faced problems as its building had been used by the college for a decade.

The officials said since its establishment in 2014, the GKMC had operated in the makeshift building of the hospital.

They said the foundation stone of the college’s own building was laid in September 2022 and the construction began soon thereafter. However, the work was later stopped several times due to shortage of funds despite the students’ urgent need to have their own building for security reasons.

The officials said the college had to rent a building outside for a boys hostel, while the girl students were accommodated inside the Bacha Khan hospital.

After the meeting, the dean, along with the project director and other officials, visited the construction site and voiced concern over the slow pace of work.

He ordered speedy construction, complaining the project has already been delayed for years. The dean warned that “more” delaying tactics of the contractor were not acceptable.

However, the contractor wondered how he could accelerate construction activities amid denial of government funding.

The participants agreed on a way forward regarding the establishment of the dental college.

Published in Dawn, March 29th, 2026

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...